Work Starts Tomorrow On Newcastle Supercars Track

Crews will work at multiple sites

Work Starts Tomorrow On Newcastle Supercars Track

Construction work associated with the Newcastle 500 Supercars track will finally begin on Monday.

Crews will be working across several sites, however the focus will be on Wharf Road which will play host to the pits.

Among the activities taking place this week:

- Establishment of contractor compounds

- Erection of temporary security fencing

- Surveying and pegging out works

- Utilities locations

- Preparation for future traffic management protocols

Traffic control measures will be in place.

Work will take place from 7am-5pm Monday to Friday and from 8am-1pm on Saturdays.

;